Here are the cost estimates from the Bryan Park Watershed Study.
Site |
Item |
Activity |
Cost |
Total |
Princeton
Creek |
Bank
Stabilization |
Land
Survey |
$
10,000 |
|
|
|
Engineering
Design |
$
19,400 |
|
|
|
Construction
Supervision |
$
6,000 |
|
|
|
Stream
Stabilization Measures |
$
179,068 |
$
214,468 |
Horsepen
Branch |
Site
6 Stream & Riparian Restorations |
Land
Survey* |
$
15,000 |
|
|
|
Engineering
Design |
$
19,800 |
|
|
|
Construction
Supervision |
$
6,000 |
|
|
|
Stream
Channel Restoration* |
$
20,500 |
|
|
|
Re-Forestation* |
$
2,000 |
$
63,300 |
Lower
Pond |
Pond
Wall Restoration & Forebay Access Road |
Survey
of Wall* |
$
10,000 |
|
|
|
Engineering
Design* |
$
10,000 |
|
|
|
Construction,
Concept II* |
$
18,956 |
|
|
|
Forebay
Access Road |
$
1,204 |
$
40,160 |
|
|
|
|
|
|
|
Total |
|
$
317,928 |
*Where the consultant gave a range of prices, this table contains the high estimate.
The consultant estimates that the Pond dredging will take another $200,000 to $500,000.
See the map for the locations of these projects. See
the Princeton Creek page for a problem the consultant
does not discuss.
Back to the Top
Last updated 02/24/02
Please send questions or comments to John
Butcher
|